Recently, the topic of calculation of liquidated damages has sparked widespread discussion on social media and legal forums. With the frequent economic activities, breach of contract disputes are increasing day by day, and understanding how to correctly calculate liquidated damages has become the focus of public attention. This article will combine the hot content of the past 10 days to provide you with a detailed analysis of the calculation method of liquidated damages and provide structured data reference.
1. Basic rules for calculating liquidated damages
According to the relevant provisions of the Civil Code, the calculation of liquidated damages must follow the following principles:
calculation factors | illustrate | Legal basis |
---|---|---|
Contractual agreement | Priority will be calculated based on the amount or proportion agreed in the contract. | Article 585 of the Civil Code |
actual loss | Liquidated damages shall not exceed 30% of the actual loss | Judicial Interpretation of the Civil Code |
Performance | Liquidated damages should be deducted accordingly for the portion that has been performed | Article 588 of the Civil Code |
2. Recent popular liquidated damages cases
In the past 10 days, the following cases of liquidated damages have triggered heated discussions among netizens:
Case type | focus of controversy | Liquidated damages ratio |
---|---|---|
Rental default | Do I need to pay full-year rent if I terminate the contract early? | 1-2 months rent |
online shopping | Liquidated damages standards for merchants’ delayed shipments | 5%-30% of the value of the product |
labor contract | Training fee compensation for employees who leave early | Converted according to the proportion of service period |
3. Examples of calculation of liquidated damages based on scenarios
The following is the calculation method of liquidated damages in different scenarios:
scene | Calculation formula | Things to note |
---|---|---|
loan contract | Principal×overdue interest rate×overdue days | Must not exceed 4 times LPR |
Commercial housing sales | Total house payment × 5/10,000 per day × number of days overdue | The maximum amount shall not exceed 20% of the total room payment. |
service contract | Unfulfilled part of the price × agreed ratio | Actual losses need to be considered |
4. Judicial practice on adjustment of liquidated damages
According to recent judicial precedents, the main factors that the court considers when adjusting liquidated damages include:
Considerations | weight | Typical cases |
---|---|---|
Degree of fault of the defaulting party | 30% | (2023)Beijing 01 Minzhong No. 1234 |
Actual losses of the non-breaching party | 40% | (2023)Shanghai 02 Minzhong No. 5678 |
Contract performance | 20% | (2023) Guangdong 03 Minzhong No. 9012 |
Industry practice | 10% | (2023)Zhejiang 01 Minzhong No. 3456 |
5. Practical suggestions
1. When signing a contract, the calculation method and upper limit of liquidated damages should be clearly agreed upon.
2. When a breach of contract occurs, collect and preserve relevant evidence in a timely manner
3. For excessively high liquidated damages, you can request the court or arbitration institution to adjust it.
4. Refer to the liquidated damages judgment standards of similar cases in the same industry